567 Clarke + Como
Only 5 penthouses remain at the intersection of life+style in Uptown Coquitlam. Sitting on floors 44-48, these homes offer spectacular views with luxurious living, steps away from the Evergreen Line.
Estimated Completion08 2021
Sales StatusNow Selling
Status.
Your at-a-glance look at how construction is coming along.
Overall Completion92%
Demolition & Foundation100%
Concrete Structure & Rough-ins100%
Steel Stud Framing & Drywall100%
Landscaping80%
Interior Finishings89%
Final Detailing79%
Timeline
Review the construction milestones underway, see which have been completed and when the rest are scheduled to be done.
-
Demolition Complete
-
Crane Erected
-
Foundation Poured
-
Excavation Complete
-
Soil Remediation Complete
-
Parking Levels 1-7 Concrete Poured
-
Mezzanine Levels Concrete Poured
-
Mezzanine Levels Ventilation Rough-ins Completed
-
Mezzanine Levels Plumbing Rough-ins Completed
-
Mezzanine Levels Electrical Rough-ins Completed
-
Mezzanine Levels Drywall Completed
-
Mezzanine Levels Cabinets Installed
-
Mezzanine Levels Countertops Installed
-
Mezzanine Levels Laminate Installed
-
Mezzanine Levels Door & Trims Installed
-
Mezzanine Levels Appliances Installed
-
Levels 3-28 Concrete Poured
-
Mezzanine Levels Final Painting Completed
-
Mezzanine Levels Final Cleaning Completed
-
Levels 3-28 Plumbing Rough-ins Completed
-
Levels 3-28 Ventilation Rough-ins Completed
-
Levels 3-28 Steel Stud Framing Completed
-
Levels 29-43 Concrete Poured
-
Levels 3-28 Electrical Rough-ins Completed
-
Levels 44-49 Concrete Poured
-
Levels 29-43 Ventilation Rough-ins Completed
-
Levels 3-28 Drywall Installed
-
Levels 3-28 Hardwood Installed
-
Levels 3-28 Doors & Trim Installed
-
Levels 3-28 Countertops Installed
-
Levels 29-43 Steel Stud Framing Completed
-
Levels 3-28 Cabinets Installed
-
Levels 44-49 Ventilation Rough-ins Completed
-
Level 3-28 Appliances Installed
-
Level 49 Roofing Completed
-
Levels 29-43 Plumbing Rough-ins Completed
-
Roof Waterproofing Finalized
-
Level 3-28 Final Painting Completed
-
Level 3-28 Final Cleaning Completed
-
Levels 29-43 Drywall Installed
-
Levels 44-49 Plumbing Rough-ins Completed
-
Levels 44-49 Electrical Rough-ins Completed
-
Levels 29-43 Cabinets Installed
-
Levels 29-43 Laminate Installed
-
Levels 29-43 Doors & Trim Installed
-
Levels 44-49 Drywall Installed
-
Level 29-43 Countertops Installed
-
Level 29-43 Appliances Installed
-
Levels 44-49 Cabinets Installed
-
Levels 44-49 Laminate Installed
-
Levels 44-49 Doors & Trim Installed
-
Levels 44-49 Countertops Installed
-
Level 29-43 Final Painting Completed
-
Level 29-43 Final Cleaning Completed
-
Level 44-49 Final Painting Completed
-
Level 44-49 Final Cleaning Completed