Mirabel
149 West End condominiums thoughtfully crafted for high-end downtown living. Located on Davie Street, this building will offer proximity to some of the best places in Vancouver.
Estimated Completion07 2021
Sales StatusNow Selling
Status.
Your at-a-glance look at how construction is coming along.
Overall Completion92%
Demolition & Foundation100%
Concrete Structure & Rough-ins100%
Steel Stud Framing & Drywall100%
Landscaping80%
Interior Finishings76%
Final Detailing64%
Timeline
Review the construction milestones, see which have been completed and when the rest are scheduled to be done.
-
Abatement Completed
-
Demolition Completed
-
Two Cranes Erected
-
Excavation Completed
-
Foundation Poured
-
Parking Level 1-4 Poured
-
Podium (Levels 1-5) Concrete Poured
-
East Tower (Levels 6-18) Concrete Poured
-
West Tower (Levels 6-19) Concrete Poured
-
Podium (Levels 1-5) Waterproof Roofing Completed
-
East Tower (Levels 6-18) Waterproof Roofing Completed
-
Podium (Levels 1-5) Steel Stud Framing Completed
-
West Tower (Levels 6-19) Steel Stud Framing Completed
-
Podium (Levels 1-5) Mechanical Rough-ins Completed
-
Podium (Levels 1-5) Electrical Rough-ins Completed
-
East Tower (Levels 6-18) Steel Stud Framing Completed
-
East Tower (Levels 6-18) Mechanical Rough-ins Completed
-
West Tower (Levels 6-19) Waterproof Roofing Completed
-
East Tower (Levels 6-18) Electrical Rough-ins Completed
-
East Tower (Levels 6-18) Rooftop Planters Completed
-
West Tower (Levels 6-19) Ventilation Rough-ins Installed
-
Podium (Levels 1-5) Drywall Completed
-
West Tower (Levels 6-19) Electrical Rough-ins Installed
-
Podium (Levels 1-5) Rooftop Planters Completed
-
East Tower (Levels 6-18) Drywall Completed
-
East Tower (Levels 6-18) Doors & Trim Installed
-
West Tower (Levels 6-19) Rooftop Planters Completed
-
Podium (Levels 1-5) Doors & Trim Installed
-
East Tower (Levels 6-18) Tile Flooring Installed
-
Podium (Levels 1-5) Tile Flooring Installed
-
West Tower (Levels 6-19) Drywall Installed
-
West Tower (Levels 6-19) Doors & Trim Installed
-
East Tower (Levels 6-18) Cabinets Installed
-
Podium (Levels 1-5) Cabinets Installed
-
Podium (Levels 1-5) Countertops Installed
-
West Tower (Levels 6-19) Tile Flooring Completed
-
West Tower (Levels 6-19) Final Paint Completed
-
West Tower (Levels 6-19) Hardwood Flooring Installed
-
West Tower (Levels 6-19) Cabinets Installed
-
Podium (Levels 1-5) Mirrors & Shower Doors Installed
-
Podium (Levels 1-5) Hardwood Flooring Installed
-
East Tower (Levels 6-18) Appliances Installed
-
West Tower (Levels 6-19) Countertops Installed
-
West Tower (Levels 6-19) Backsplash Tile Installed
-
Podium (Levels 1-5) Appliances Installed
-
East Tower (Levels 6-18) Carpet Installed
-
East Tower (Levels 6-18) Final Paint Completed
-
West Tower (Levels 6-19) Appliances Installed
-
Podium (Levels 1-5) Carpet Installed
-
East Tower (Levels 6-18) Homeowner Walkthroughs Completed
-
West Tower (Levels 6-19) Final Cleaning Completed
-
West Tower (Levels 6-19) Homeowner Walkthroughs Completed
-
Podium (Levels 1-5) Final Painting Completed
-
East Tower (Levels 6-18) Final Clean Completed
-
Building Occupancy Issued
-
Podium (Levels 1-5) Final Cleaning Completed
-
Podium (Levels 1-5) Homeowner Walkthroughs Completed
Gallery.
Photos of construction in progress, from beginning to end.