Your at-a-glance look at how construction is coming along.

Overall Completion35%

Demolition & Foundation100%

Framing & Roofing66%

Rough-ins & Drywall 36%

Landscaping0%

Interior Finishes0%

Final Detail0%

Timeline

Review the construction milestones, see which have been completed and when the rest are scheduled to be done.

  • Building 6 Framing to Trusses

  • Heritage House prepare existing for framing

  • Building # 1 - Framing to trusses

  • Building # 6 - Plumbing rough-ins

  • Building # 6 - Electrical rough-ins

  • Building # 5 - Framing to trusses

  • Building # 1 - Electrical rough-ins

  • Building # 2 - Framing to trusses

  • Heritage House - Exterior brickwork

  • Building # 6 - Painting prime and base coat

  • Building # 5 - Electrical rough-ins

  • Building # 4 - Framing to trusses

  • Heritage House - Cabinet install

  • Play area - Detail excavation

  • Building # 2 - HVAC & AC rough-ins

  • Building # 5 - Exterior painting

  • Play area - Concrete work

  • Building # 6 - Counter tops

  • Building # 2 - Exterior railings

  • Building # 6 - Tile work to tubs, entries and backsplash

  • Play area - Play equipment

  • Building # 4 - Electrical rough-ins

  • Building # 3 - Roofing contractor

  • Building # 1 - Counter tops

  • Park - Concrete stairs and sidewalks

  • Building # 2 - Drywall board mud and tape

  • Park - Table tennis install

  • Play area - Stepping stones and wood benches

  • Building # 6 - Appliances

  • Building # 3 - Electrical rough-ins

  • Park - Fire pit install

  • Park - Trees & bushes

  • Play area - Plants and grass

  • Building # 5 - Counter tops

  • Park - Sod and grass

  • Building # 2 - Cabinet install

  • Building # 1 - Appliances

  • Building # 6 - Final clean

  • Building # 4 - Closet shelving install

  • Building # 4 - Drywall QC & touchup

  • Building # 3 - Exterior painting

  • Building # 3 - Drywall board mud and tape

  • Building # 1 - Final clean

  • Building # 3 - Painting prime and base coat

  • Building # 1 - Marcon QC

  • Building # 5 - Final clean

  • Building # 5 - Appliances

  • Building # 5 - Marcon QC

  • Building # 2 - Mid coat painting

  • Building # 2 - Final clean

  • Building # 2 - Marcon QC

  • Building # 4 - Carpeting

  • Building # 3 - Counter tops

  • Building # 4 - Final clean

  • Building # 4 - Marcon QC

  • Building # 3 - Final clean

  • Building # 3 - Appliances

  • Building # 3 - Marcon QC