Estimated Completion12 2021

Sales StatusPresale

Status.

Your at-a-glance look at how construction is coming along.

Overall Completion53%

Demolition & Foundation100%

Framing & Roofing100%

Rough-ins & Drywall 77%

Landscaping11%

Interior Finishes0%

Final Detail0%

Timeline

Review the construction milestones, see which have been completed and when the rest are scheduled to be done.

  • Building 6 Framing to Trusses

  • Heritage House - Prepare existing for framing

  • Building # 5 - Framing to trusses

  • Building # 1 - Framing to trusses

  • Building # 6 - Plumbing rough-ins

  • Building # 6 - Electrical rough-ins

  • Building # 4 - Framing to trusses

  • Heritage House - Exterior brickwork

  • Building # 1 - Electrical rough-ins

  • Building # 3 - Framing to trusses

  • Building # 6 - Painting prime and base coat

  • Building # 5 - Electrical rough-ins

  • Building # 3 - Roofing contractor

  • Building # 4 - Electrical rough-ins

  • Building # 1 - Painting prime and base coat

  • Park - Table tennis install

  • Building # 2 - Exterior painting

  • Heritage House - Cabinet install

  • Building # 5 - Exterior painting

  • Heritage House - Laminate flooring

  • Park - Sod and grass

  • Building # 6 - Exterior painting

  • Building # 6 - Counter tops

  • Building # 1 - Exterior painting

  • Building # 5 - Painting prime and base coat

  • Building # 1 - Tile work to tubs, entries and backsplash

  • Building # 2 - Painting prime and base coat

  • Building # 1 - Counter tops

  • Building # 4 - Painting prime and base coat

  • Building # 4 - Exterior painting

  • Play area - Concrete work

  • Building # 3 - Drywall board mud and tape

  • Building # 6 - Planting & Grass

  • Heritage House - Final clean

  • Building # 3 - Painting prime and base coat

  • Play area - Play equipment

  • Building # 6 - Appliances

  • Play area - Rubber floor

  • Building # 5 - Counter tops

  • Building # 3 - Planting & Grass

  • Building # 2 - Counter tops

  • Building # 4 - Countertops

  • Building # 1 - Appliances

  • Play area - Stepping stones and wood benches

  • Building # 6 - Final clean

  • Building # 6 - Marcon QC

  • Play area - Final irrigation

  • Building # 2 - Appliances

  • Building # 1 - Final clean

  • Building # 1 - Marcon QC

  • Building # 4 - Final clean

  • Building # 4 - Appliances

  • Building # 2 - Final clean

  • Building # 5 - Final clean

  • Building # 5 - Marcon QC

  • Building # 2 - Marcon QC

  • Building # 3 - Marcon QC

  • Building # 4 - Marcon QC

  • Building # 3 - Final clean