567 Clarke + Como

Only 6 penthouses remain at the intersection of life+style in Uptown Coquitlam. Sitting on floors 44-48, these homes offer spectacular views with luxurious living, steps away from the Evergreen Line.

Learn more

Register for project updates

Estimated Completion04 2021

Sales StatusNow Selling

Status.

Your at-a-glance look at how construction is coming along.

Overall Completion67%

Demolition & Foundation100%

Concrete Structure & Rough-ins55%

Steel Stud Framing & Drywall28%

Landscaping0%

Interior Finishings12%

Final Detailing0%

Timeline

Review the construction milestones, see which have been completed and when the rest are scheduled to be done.

  • Demolition Complete

  • Crane Erected

  • Foundation Poured

  • Excavation Complete

  • Soil Remediation Complete

  • Parking Levels 1-7 Concrete Poured

  • Mezzanine Levels Concrete Poured

  • Mezzanine Levels Ventilation Rough-ins Completed

  • Mezzanine Levels Plumbing Rough-ins Completed

  • Mezzanine Levels Electrical Rough-ins Completed

  • Mezzanine Levels Drywall Completed

  • Mezzanine Levels Cabinets Installed

  • Mezzanine Levels Countertops Installed

  • Mezzanine Levels Laminate Installed

  • Mezzanine Levels Door & Trims Installed

  • Mezzanine Levels Appliances Installed

  • Levels 3-28 Concrete Poured

  • Mezzanine Levels Final Painting Completed

  • Mezzanine Levels Final Cleaning Completed

  • Levels 3-28 Ventilation Rough-ins Completed

  • Levels 3-28 Steel Stud Framing Completed

  • Levels 3-28 Plumbing Rough-ins Completed

  • Levels 3-28 Electrical Rough-ins Completed

  • Levels 29-43 Concrete Poured

  • Levels 3-28 Drywall Installed

  • Levels 3-28 Cabinets Installed

  • Levels 3-28 Countertops Installed

  • Levels 29-43 Ventilation Rough-ins Completed

  • Levels 29-43 Steel Stud Framing Completed

  • Level 49 Roofing Completed

  • Levels 29-43 Plumbing Rough-ins Completed

  • Levels 3-28 Doors & Trim Installed

  • Levels 29-43 Electrical Rough-ins Completed

  • Roof Waterproofing Finalized

  • Levels 44-49 Ventilation Rough-ins Completed

  • Level 3-28 Final Painting Completed

  • Levels 29-43 Drywall Installed

  • Level 3-28 Final Cleaning Completed

  • Level 44-48 Steel Stud Framing Completed

  • Levels 44-49 Plumbing Rough-ins Completed

  • Levels 44-49 Electrical Rough-ins Completed

  • Levels 29-43 Cabinets Installed

  • Level 29-43 Countertops Installed

  • Levels 44-49 Drywall Installed

  • Levels 3-28 Laminate Installed

  • Levels 29-43 Doors & Trim Installed

  • Level 29-43 Appliances Installed

  • Levels 29-43 Laminate Installed

  • Levels 44-49 Countertops Installed

  • Level 29-43 Final Painting Completed

  • Level 29-43 Final Cleaning Completed

  • Levels 44-49 Laminate Installed

  • Level 44-49 Appliances Installed

  • Levels 44-49 Doors & Trim Installed

  • Level 44-49 Final Painting Completed

  • Level 44-49 Final Cleaning Completed

  • Homeowner Walkthroughs Completed